House in Surin

#9
update pictures few more pictures
Seems things can happen quickly here. All it takes is knowledgable guys and the proper equipment. I don’t think my builder had either. Although we are living here now.
I think it took about a month to dig the 23 holes to put the polls in. Maybe deeper though. We never saw a cement truck until the day we poured our driveway. By then the house was built, yard was fenced in and they had no place left to dump their sand, gravel and cement bags.
Our builder told us 5 months as well. Last month November it was one year
 
#10
few more pictures walls almost completed .
 

Attachments

#16
More pics from today
 

Attachments

#17
Completed all but the kitchen , waiting for Boontavorn to complete 6 weeks late .
 

Attachments

#18
more
 

Attachments

#19
It came together very nicely Alan. What is the delay with Boontavorn? 6 weeks is not acceptable. I noticed in one of the washrooms to the left side of the toilet, or right side if you’re sitting on it, there appears to be a white box. Is that the hot water? What are your landscaping plans? I’ll be excited to see how that turns out. Take care ...


Sent from my iPad using Tapatalk